Drawing revisions: the cloud, the delta and the block

The same drawing, with the same geometry, means different things depending on what it was issued for and which revision it is. The most important mark on a sheet is not the north arrow or the scale: it is the triangle with a number in it, because it is the only one that tells you whether what you are looking at is what is being built.

A drawing is not a picture: it is a document with a state

A drawing issued for review binds nobody. One issued for construction does, and whoever builds something else answers for it. The geometry can be identical; what changes is the commitment.

Issue stateWhat it meansCan you price from it?
For review
or comment
Marks are expected on it. It is still being argued about Not firm. An order of magnitude at most
For coordination Goes to the other disciplines to be cross-checked. The scheme should be settled No. Its own author does not consider it settled yet
For permit Satisfies what the authority requires. Careful: it may lack construction detail With care. Information the site needs is missing
For bid This is the priced set. Anything asked here is answered by addendum Yes. That is exactly what it is for
For construction The governing set. From here on, every change leaves a trail and usually an invoice Yes, and it is what gets built

The right question about a drawing is never «is this up to date?». It is «what was it issued for, and when?».

Watch the abbreviation IFC: in this trade it means two different things and both turn up in the same email — the model exchange format, and a drawing state, Issued For Construction. When somebody writes «send me the IFC», ask which one. It is not a silly question.

The three marks of a revision

When a drawing is reissued, being new is not enough. It has to say what changed, where and why. There is a language for that, it is essentially the same everywhere, and it is three marks that only work together.

2 No DATE DESCRIPTION BY 215-03-26 Wall grid C · RFI 042JS 102-02-26 Addendum 1JS 010-01-26 Issued for constructionJS The cloud Encloses exactly what changed The delta Says which revision that cloud belongs to The block The history: number, date, reason and author
The three are read together: the cloud says where, the delta says when, and the block says why and who. If any one of them is missing, the revision cannot be audited.

The rules almost nobody writes down

Addendum, ASI, change order: what each one is

Every document that modifies a project falls into one of two worlds, and the line between them is contract signature. Confusing them means confusing who pays.

DocumentWhenWhat it doesDoes it change the price?
AddendumBefore signing Modifies the bid documents while pricing is still open. Every bidder receives it No: it is priced in. If you missed it, you pay the difference
RFIAfter A question to the designer. Its answer can trigger everything else On its own, no
Supplemental
instruction
After Clarifies without changing scope It should not. If extra work is slipped in, say so in writing the same day
Proposal
request
After You are asked to price a change. Not approved yet Not yet. It is a quotation
Change orderAfter Signed by both parties. It amends the contract Yes, and the time as well if applicable
Construction
change directive
After The owner directs the work before the price is agreed Yes, but settled later. Keep records of everything
The day you start making a change without paperwork is the day you decided to pay for it. It does not matter whether you are right. It matters whether you have the document.

Traceability: where every number came from

All of the above exists for this. A quantity, a price or a date is only as good as your ability to reconstruct where it came from. And reconstructing means answering three things without hesitating: which sheet, which revision and which date.

Origin
Sheet A-201 · Rev 2 · 2026-03-15
Issued for construction. It is the document, not «the drawing somebody sent me».
measured from
Take-off
340 m² of masonry · Level 7 · Zone B
With its unit defined and its location. Without location the chain breaks here.
rolls up into
Estimate
Division 05 · Masonry
Quantity times unit price, with the estimate class declared.
sets the duration of
Schedule
Masonry level 7 · week 12
Quantity divided by production rate and crews. The date was not invented.
gets billed in
Payment
Progress application no. 4
You bill the quantity installed, in the same unit, with the photo that backs it.

Somebody points at any number in your estimate and you have to reach the drawing in under a minute. If you cannot, you do not have traceability. You have memory.

What to do when a new revision lands

This is where more money is lost than in any measurement error. Revision 3 of sheet A-201 arrives. The correct sequence is:

The fact that settles contracts: the bid was priced on revision 1 and the site is building revision 3. That difference is somebody's money. If nobody kept the record, it is yours.

Frequently asked questions

What is a revision cloud?

The wavy line enclosing exactly the area of the drawing that changed since the previous issue. It always travels with a delta triangle carrying the revision number, so you know which revision it belongs to, and its reason is spelled out in the revision block in the title block.

What is the difference between an addendum and a change order?

An addendum comes before contract signature: it modifies the bid documents while pricing is still open, every bidder receives it, and it is priced in — it costs nothing extra. A change order comes after: it amends a signed contract, is signed by both parties, and does change the price and, where applicable, the time.

Can you price from a drawing issued for coordination?

Not firmly. Its own author does not consider that sheet settled: it is circulating so the other disciplines can cross-check it. The issue state is printed on the sheet itself, and it is the first thing to read before measuring anything.

Why do some revisions use letters and others numbers?

It is an office convention rather than a universal standard, but a very widespread one: letters (A, B, C) during design, before issue for construction, and numbers (1, 2, 3) after. When you see one, you know which side of that line the document sits on.

What happens if two revisions of the same sheet are in circulation?

Somebody is building the wrong one. That is why a superseded sheet is actively withdrawn rather than left around «just in case»: the cost of the old version being available is always higher than the cost of losing it.

Every number, with its origin

VDClens carries a construction project from the model to the site in one application. Every quantity stays tied to the sheet, the revision and the date it came from — which is what this guide is about.