Project phases: SD, DD, CD and what they mean

The same point of project maturity has five or six different names depending on the country, the sector, and the year the contract was written. These are not different methodologies. They are different vocabularies. This guide translates them, and explains what you can honestly promise at each one.

Why a project has phases

A project is not designed from less to more detail out of habit or bureaucracy. It works that way because every decision makes the decisions after it more expensive. Choosing the structural system in month one costs a meeting. Changing it in month fourteen costs redoing the MEP, the façade, the foundations and the budget.

Phases exist to put doors in the way: moments where the project freezes enough that the next layer of work can rest on it without fear. Without those doors, everybody builds on sand and everybody does it twice.

A phase is not a period of time. It is an agreement about what is no longer up for discussion.

Which leads to the practical consequence: the effort you put into a task has to match the phase the project is in. Measuring to three decimal places off a drawing that is still going to change is not rigor. It is work that will be thrown away, and it manufactures a confidence the number has not earned.

The equivalence table

This is the translation that prevents half the misunderstandings between teams in different countries. The first column is the only real thing. The rest is what it happens to be called in the contract in front of you.

Project maturity Buildings · AIA
(United States)
United Kingdom
RIBA 2020
Civil works
(percentages)
Industrial
(process)
Latin America
and Spain
Idea and briefPre-design · ProgrammingStages 0–1 Concept · 15%FEL 1 · ConceptualPrefactibilidad
General schemeSD · Schematic Design Stage 2 · Concept Design30%FEL 2Anteproyecto
Definition and coordinationDD · Design Development Stage 3 · Spatial Coordination60%FEL 3 · FEED Proyecto básico
Documents to build fromCD · Construction Documents Stage 4 · Technical Design90% → 100%Detailed engineering Proyecto ejecutivo
TenderBidding & NegotiationEnd of Stage 4 Bid documentsEPC awardLicitación
ConstructionCA · Construction Administration Stage 5ExecutionConstruction and commissioning Obra · Interventoría
Handover and useClose-outStages 6–7Acceptance Start-upEntrega · Operación

Three details worth the whole table

When a client asks for «el proyecto básico» and you work in SD, DD and CD, they are not asking for anything unusual: they are asking for DD. The expensive part is not the language barrier. It is delivering the wrong phase.

What each discipline delivers in each phase

The phases are the same for everyone, but «being in DD» means very different things depending on whether you are the architect, the structural engineer, the MEP engineer or civil. And since the budget and the schedule feed off all of them, this table is what lets you work out which discipline the gap is coming from when something does not add up.

DisciplineSDDDCDCA
Architecture Scheme, areas, envelope, general plans Dimensioned plans, sections, elevations, wall types, defined fenestration Construction details, door, window and finish schedules, specifications RFI responses, submittal review, record drawings
Structure Structural system chosen, spans, preliminary sizing Member sizes fixed, loads coordinated, foundation scheme Reinforcement drawings, schedules, notes and specifications Shop drawing approval, testing, rebar acceptance
MEP Estimated loads, space reserved for equipment, conceptual services Main routing, equipment selected, plant rooms sized Installation drawings, final sizes, supports, single-line diagrams Fabrication drawing approval, testing, commissioning
Civil and site Siting, general levels, access, preliminary earthworks Profiles, external utilities, drainage, paving Final sitework quantities, utility details Grade control, compaction testing, utility acceptance
Estimating Parametric or cost-per-area estimate. Class 4 or 5 Measurable quantities by system. Class 3 Quantities by line item with unit price analysis. Class 2 or 1 Control against actuals, change orders, final account
Scheduling General milestones and overall duration Sequence by work front, preliminary rates Detailed schedule with supported durations Updates, actual progress, delay analysis

A project is almost never in a single phase. It is in DD for architecture, SD for MEP and CD for structure, all on the same day.

Which produces the rule almost nobody applies: a project's phase is the minimum, not the average. If you are taking off MEP quantities and MEP is in SD, it does not matter that architecture is in CD. Your number is an SD number, and it should be delivered as one.

How firm can a budget be at each phase

There is an international scale for stating how firm a cost number is. It comes from the process industries, where being wrong at the wrong stage costs hundreds of millions, and it is used worldwide under the name estimate classes.

ClassProject definitionWhat it is for Typical range
Class 5Essentially nothing defined Screening whether it is worth thinking about±20 to 50%
Class 4General concept Feasibility study±15 to 30%
Class 3Design defined at system level Budget authorization±10 to 20%
Class 2Advanced design, measurable quantities Control and bidding±5 to 15%
Class 1Complete documents Firm bid, check estimate±3 to 10%

The ranges vary by sector: buildings and process industries publish different tables. What does not vary is the idea that a number travels with its uncertainty.

A number without its class is not an estimate. It is an opinion with two decimal places.

How this is used in practice

The hard conversation is never «the project went up». It is «you gave me a number». If the number went out with its class and its date, that conversation does not happen. If it went out bare, you will have it, and you will lose it.

The most common mistakes

Frequently asked questions

What do SD, DD and CD mean?

They are the three design phases in the American system. SD (Schematic Design) is the general scheme, DD (Design Development) is definition and coordination between disciplines, and CD (Construction Documents) is the set you build from. They correspond to anteproyecto, proyecto básico and proyecto ejecutivo respectively.

What is the difference between Schematic Design and Design Development?

SD settles what the building is: massing, areas, layout, the structural system. DD settles how it works: dimensions fixed, systems routed, equipment selected, disciplines coordinated against each other. The clearest test is that in SD you can still change the scheme; in DD you can only change details of it.

How do 30%, 60% and 90% design map to SD, DD and CD?

Roughly, 30% corresponds to SD, 60% to DD, and 90–100% to CD. But the percentages do not measure effort spent: they name packages of deliverables defined by contract.

What is FEED?

Front End Engineering Design, the definition phase in the process and industrial world. It corresponds roughly to DD, and it is usually the stage on which the final investment decision is taken.

Can you give a budget at SD?

Yes, as long as you state its class. At SD a reasonable estimate is Class 4 or 5, with a range that can reach ±30% or more. What you cannot do is issue that number without declaring its uncertainty: whoever receives it will treat it as final.

Can a project be in two phases at once?

It almost always is. Architecture in CD, structure in DD and MEP in SD within the same project is normal. For the purposes of what can be promised, the project's phase is that of the least advanced discipline, not the average.

Every number, with its origin